Update Village School House Project Cambodia with Smiling Gecko
In December 2016, the planning of the architecture by the team under the direction of Prof. Dirk E. Hebel was completed with a ready-to-go, realizable project. The adaptation to the local regulations and the approval of the project were also finalized in spring 2017. In April 2017, the earthworks started. First of all, the whole school area had to be raised. The construction site is huge and we will be moving 600’000 m3 of soil. The result is a lake of 110,000m3 which will be used for the irrigation of our agricultural projects in the future. Although the rainy season, which had started too early, leads to delays, we are sure to be able to take up the school operation with the kindergarten and the first school year in November17. More information here.